Transpower’s October update reports new generating capacity entering commissioning, with further projects still in delivery. Connection milestones, energy production and dependable peak-period output remain distinct measures of supply.
Key developments
Commissioning is being measured differently. In its 15 October newsletter, Transpower reported that 15 projects with combined capacity of 1,002 MW began generating between October 2025 and October 2026. Its revised reporting covers grid-connected projects that have been energised and embedded projects of at least 10 MW that started customer-asset commissioning. This rolling measure replaces reporting focused on projects moving out of delivery, so a comparison with earlier monthly snapshots could misstate the pace of change. [1]
Further projects remain in delivery. Transpower’s connections register, dated 8 October and checked at the research cutoff, identifies 16 new generation projects in delivery, representing 3,342 MW. Connection counts differ from technology counts because projects may combine resources such as solar and storage. This is a project pipeline, not electricity already available to consumers, and cannot simply be added to the commissioning total. [2]
Hydro remains the largest source of generation. Transpower’s report for the week ended 11 October recorded solar production of 21 GWh, or 2.7% of its reported generation mix. Hydro supplied 65%, illustrating the continuing weight of existing assets alongside newer generation. The same report explains that generation-balance assessments account for outages, available capacity and weather-related demand. The operational question is how much new capacity will be available when demand is high or other generators are offline. [3]
A larger connection pipeline could increase supply over time, but the weekly generation mix is the better evidence of what those assets are delivering today.
Prices and data
| Indicator | Observation | Observation date | Release and verification |
|---|---|---|---|
| Ōtāhuhu average spot price | NZ$60/MWh | Week ended 11 Oct 2026 | 13 Oct release; checked 19 Oct [3] |
| Solar generation | 21 GWh | Week ended 11 Oct 2026 | 13 Oct release; checked 19 Oct [3] |
| Delivery stage capacity | 3,342 MW | 8 Oct 2026 | Register checked 19 Oct [2] |
Prices are historical observations, not quotations for 19 October 2026. Capacity in MW is not directly comparable with energy generated in GWh.
Week ahead: 26 October–1 November 2026
• Any commissioning updates showing projects moving from initial energisation to sustained operation, or changes to expected completion dates.
• Solar output alongside daytime wholesale prices. Weekly averages can obscure changes within the trading day.
• Changes to generation-balance and outage forecasts, particularly whether additional capacity is available during tight periods. No specific project completion is assumed during the watch period.
Sources
[1] Transpower October 2026 newsletter. Published 15 October 2026.
[2] Transpower grid connections register. Snapshot 8 October; verified 19 October 2026.
[3] Transpower Market Operations Weekly Report. Week ended 11 October; released 13 October 2026.